Most building work in NSW needs approval before it starts. For homes, extensions and small developments, there are two main routes: a complying development certificate (CDC) or a development application (DA). Picking the right one early can save months. The NSW Government is also proposing changes that would open the faster route to more projects.
What is a complying development certificate?
A CDC is a combined planning and construction approval for straightforward development. If a proposal meets every standard in the State Environmental Planning Policy (Exempt and Complying Development Codes) 2008, known as the Codes SEPP, it can be approved without a full merit assessment.
Your council or an accredited certifier can issue a CDC. The NSW Government says a CDC can be approved in as little as 20 days, or 10 days for designs from the NSW Housing Pattern Book. Kiama Council, for example, aims to decide on complying development applications within 20 days.
Common CDC projects include:
- New dwelling houses, and alterations and additions to existing homes
- Dual occupancies, manor houses and terraces under the Low Rise Housing Diversity Code, which applies only in R1, R2, R3 and RU5 zones where the council’s LEP (Local Environmental Plan) already allows that housing
- Pools, sheds and other ancillary structures
- Demolition, some changes of business use and some new industrial buildings
Neighbours are notified 14 days before a standard CDC is approved, or at least 7 days before approval under the Pattern Book pathway.
What is a DA?
A DA asks your council, or another consent authority, for development consent. It’s assessed on merit under section 4.15 of the Environmental Planning and Assessment Act 1979. The assessment weighs impacts on neighbours, the environment, local character and the public interest.
That makes a DA more flexible than a CDC. Development control plan (DCP) controls can be applied flexibly, and a clause 4.6 request can ask to vary an LEP standard such as height or floor space ratio. The trade-off is time. The NSW Government puts the average DA assessment at around 80 days. A DA consent is also planning approval only. You still need a construction certificate before building work begins.
Since 1 September 2026, the statewide Community Participation Plan sets exhibition rules for DAs. Many lower-impact proposals, such as dual occupancies of up to two storeys, secondary dwellings and subdivisions creating no more than 5 lots, no longer go on exhibition. Most others are exhibited for at least 14 days.
| Feature. | CDC. | DA. |
| Who decides | Council or an accredited certifier | Council or another consent authority |
| How it’s assessed | Against fixed standards in the Codes SEPP | On merit under section 4.15 |
| Typical timeframe | As little as 20 days | Around 80 days on average |
| Flexibility | Every standard must be met | Controls can be varied with justification |
| Construction approval | Included | Separate construction certificate needed |
| Neighbours | Notified 14 days before approval | Exhibited for at least 14 days, unless the type is excluded |
Table 1: CDC and DA compared.
When can you use a CDC?
A project has to pass three tests.
- The development type is in the Codes SEPP. If the code doesn’t cover the type of work, a DA is needed.
- The land isn’t excluded. Shoalhaven City Council lists heritage items and draft heritage items, foreshore areas, environmentally sensitive areas and bush fire prone land rated BAL-40 or BAL-FZ as land where complying development can’t be used. A Section 10.7 planning certificate will show which constraints apply to your site.
- Every standard is met. Setbacks, building height, landscaped area and floor area all have to comply. Miss one and the whole project becomes a DA. The NSW Government estimates that failing a single standard adds more than 60 days on average.
Other approvals can still apply under either pathway. Works on a driveway crossover or kerb need a section 138 approval under the Roads Act 1993. Water, sewer and stormwater connections may need a section 68 approval under the Local Government Act 1993.
How long do DAs take in our region?
Assessment times vary between councils. In round 2 of the NSW Government’s Faster Assessments Incentive Program, Shellharbour City Council averaged 58 days and Shoalhaven City Council 104 days for the 2025 to 2026 financial year. Wollongong City Council narrowly missed the program’s 105-day benchmark. Kiama isn’t part of the program, which only covers councils with housing targets above 1,000 homes.
For a compliant project, a CDC can still be the quicker option in all four council areas.
What’s changing in 2026?
From 14 May to 24 June 2026, the NSW Government exhibited two proposals that would sit between a CDC and a full DA.
Variations to complying development
Councils could approve minor variations to certain Codes SEPP standards, including setbacks, heights, maximum gross floor area and vehicle access. The first stage would cover low-rise housing under Parts 3, 3A, 3B, 3C and 3D of the Codes SEPP.
- Up to three or four standards could be varied per development, including any later modifications.
- Only councils would assess variations. Where a variation is identified upfront, a private certifier would complete an initial check before passing it to council.
- A CDC that includes a variation certificate would be decided within 20 calendar days.
- Two fee options are proposed: a flat fee of $456, or $342 to $569 depending on how many standards are varied.

Figure 1: Existing complying development process and CDC with variations (Summary of the EIE, page 1).
| Development standard. | Proposed variation. |
| Maximum building height | Up to 8.5 m to 9 m for dwellings, dual occupancies and manor homes, and 9 m to 9.5 m for terraces, where consistent with LEP height limits. |
| Maximum gross floor area | Up to 10% more than the maximum GFA for dwellings, dual occupancies, manor homes, terraces and detached studios. An extra 15 to 20 m² for detached development such as decks and sheds. |
| Primary road setbacks | May vary where consistent with the established street setback or council DCP controls. |
| Side setbacks | Additions may align with the existing side setback or 0.9 m, whichever is greater. Lower levels may reduce to 0.9 m where consistent with the DCP. Reduced setbacks for upper-level parts of dual occupancies and manor homes 10 m behind the building line, and some narrower lots under the Inland Code. |
| Rear setbacks | Upper-level rear setbacks may vary where consistent with the DCP or the average of the 2 adjoining dwellings within 40 m. Dual occupancy upper storeys may match adjoining dwellings, or reduce by 2 m where impacts on neighbours are minimal. |
| Primary road articulation zone | Balconies, decks, pergolas, terraces, verandahs and façade features can take up to 50% of the building width, up from 25% of lot width. |
| Privacy screens | Not required where there is no direct line of sight into a neighbouring habitable room window or principal private open space. |
| Garage door widths | Car parking may align with the building line. Garage doors up to 5 m wide for two-storey dwellings on 10 to 12 m wide lots, where parking is integrated, not visually dominant and served by a single tapered driveway. |
| Building design | Two-storey dwellings on lots under 11 m wide don’t need a ground-floor street-facing habitable room window if the upper level has street-facing windows or balconies. |
| Dual occupancy lot width and access | Attached two-storey dual occupancies on 12 to 15 m wide lots may take access from a primary road, with each garage door no more than 3 m wide. |
| Swimming pools | Allowed in the secondary road setback on corner lots for dwellings and dual occupancies, and forward of the building line in rural zones behind DCP or Rural Housing Code front setbacks. |
| Tree protection | Allowed within 3 m of a protected tree on the site or adjoining land, where an arborist report sets an appropriate setback and the design follows it. |
Source: NSW Department of Planning, Housing and Infrastructure, Summary of the Explanation of Intended Effect: Variations and changes to complying development (May 2026), pages 2 to 3. These are proposed changes and are not yet in force.
A targeted assessment pathway
A new low-rise housing code would let one and two storey homes, dual occupancies and multi dwelling housing that don’t meet the CDC test be assessed as a streamlined DA, with a target of 50 days. Assessment would focus on compliance with the code rather than reopening broader questions settled at the strategic planning stage. Heritage items and heritage conservation areas would be excluded.
Neither change is in force yet. The Department is reviewing submissions on the variations and expects to finalise them later this year. Targeted assessment needs a further Explanation of Intended Effect (EIE) and a SEPP declaration before it can be used.
What this means for developers
- Test the CDC pathway first. For a compliant dwelling, dual occupancy or extension, a CDC is usually the faster and more predictable route.
- Small misses still matter. Until variations commence, missing a single standard means a DA. Designing to the Codes SEPP from the first sketch avoids that.
- Know your land before you design. A planning certificate, bushfire attack level and flood information will tell you early whether a CDC is possible.
- Don’t hold projects for the reforms. There’s no confirmed start date, and the first stage only covers low-rise housing.
- A DA is still the right choice for some sites. Heritage, steep or constrained land, larger yields and designs that need a clause 4.6 variation are often better suited to a merit assessment.
How Allen Price can help
Our town planning team can check whether your project qualifies for a CDC, identify any land-based exclusions, and prepare a Statement of Environmental Effects when a DA is the better route. Our surveyors provide the detail and contour surveys needed to confirm setbacks and heights, and our civil engineers design the stormwater and driveway works both pathways require. Get in touch with our Nowra, Kiama or Wollongong office to talk through the right approval for your next project.