What’s changing
From 1 September 2026, how development applications are notified and exhibited in NSW is set by one statewide document. The new statewide Community Participation Plan (CPP) replaces more than 100 separate plans that applied across the state. Those included the individual plans that Wollongong, Shellharbour, Kiama and Shoalhaven councils had each prepared. Shoalhaven had only adopted its updated plan in May 2025.
A CPP sets out how and when a planning authority must involve the community before deciding a DA, a planning proposal or a strategic plan. Until now, each council wrote its own. That meant notification rules could differ between neighbouring council areas. The Government’s own example was that two sides of the same street could have different consultation requirements.
The new plan does two main things. It sets one minimum exhibition period for each type of application across NSW. It also lists lower-impact development types that no longer need to go on exhibition at all.
Key summary
Commenced: 1 September 2026
Local DAs: exhibited for a minimum of 14 days
Council-related DAs: a minimum of 28 days
Planning proposals, draft DCPs and draft contributions plans: a minimum of 28 days
Regional plans and local strategic planning statements: a minimum of 60 days
Excluded from exhibition: development types listed in Table 6 of the plan, provided they don’t need a clause 4.6 variation to building height or floor space ratio

Figure 5: Exhibition process for local development (Community Participation Plan, page 19).
Which DAs no longer go on exhibition
This is the change most developers and builders will notice. Table 6 of the CPP lists development types that don’t need public exhibition. For these, councils don’t send neighbour notification letters and don’t invite formal submissions.
Types most relevant to residential and small-scale development in our region include:
- Dwelling houses and dual occupancies of up to two storeys
- Attached dwellings and multi dwelling housing of up to 5 dwellings
- Secondary dwellings
- Subdivisions creating no more than 5 new lots
- Pools, sheds, pergolas, carports and other ancillary development to existing homes
- Alterations and additions to existing homes that result in no more than two storeys
- Demolition and tree removal on private land
- Changes of use, except to a registered club or pub, or where the site is in or adjoins a residential zone
- Modifications under sections 4.55(1) and 4.55(1A), minimal-impact modifications under 4.56(1), and 4.55(2) modifications to consents for the listed development types
There are two important conditions. First, the exclusion is lost if the application needs a variation to the height of building or floor space ratio standard under clause 4.6. In that case, the DA must be exhibited for at least 14 days. Second, the exclusions don’t apply to designated development, nominated integrated development, threatened species development or State significant development.. Residential flat buildings and shop top housing development types will remain subject to the 14-day exhibition.
The plan also makes clear that skipping the exhibition doesn’t mean a lighter assessment. Councils must still assess these DAs on their merits, including privacy, overshadowing and heritage significance.
What still gets exhibited, and for how long
Anything not in Table 6 still goes on exhibition, with set minimum periods.

Table 5: Public exhibition timeframes for development applications (Community Participation Plan, page 23).
Following feedback on the draft, residential flat buildings and shop top housing will keep a minimum 14-day exhibition period. Councils can also go beyond the minimums. Where an application is likely to generate significant public interest because of its location, nature or scale, the consent authority can exhibit it for longer.
A few timing rules are worth knowing:
- Exhibition periods are counted in calendar days, including weekends.
- The period from 20 December to 10 January (inclusive) doesn’t count towards an exhibition period. A DA that starts exhibition in mid-December will run well into January.
- Anyone can give feedback on an application at any stage. For DAs that aren’t exhibited, that feedback isn’t treated as a formal submission, and the council doesn’t have to consider submissions in its assessment.
What it means across the Illawarra and Shoalhaven
For our region, the biggest shift is consistency. Exhibition rules for a dual occupancy in Dapto, Albion Park, Gerringong or Ulladulla are now the same. Before, the answer depended on which council’s plan applied and how it was written.
Councils still have a role in how they engage. They can keep using their own engagement strategies to choose methods such as letters, site notices and drop-in sessions, but those strategies can no longer set exhibition timeframes.
The plan also puts more weight on strategic planning. Longer minimum periods apply to the documents that decide where growth happens, such as regional plans, local strategic planning statements and planning proposals. For landowners with sites earmarked for future rezoning, those strategic exhibitions are now the main opportunity to have a say.
What this means for developers.
- Small projects can move sooner. A compliant two-storey dual occupancy, a secondary dwelling or a subdivision of up to 5 lots can skip the exhibition stage altogether.
- A clause 4.6 variation changes the pathway. Asking to vary height or FSR puts an otherwise excluded DA back on a 14-day exhibition. It’s worth testing early whether a design can sit within the standards.
- Neighbours may still be heard. Feedback can still reach the council outside exhibition, and assessment still covers amenity impacts. A conversation with neighbours before lodging remains good practice.
- Plan around Christmas. With the 20 December to 10 January exclusion, any DA that needs exhibition should ideally be lodged by late November to avoid a long pause.
- Bigger projects are largely unchanged. Residential flat buildings, shop top housing and larger multi dwelling developments still need at least 14 days, and councils can extend that for higher-interest proposals.
Where it stands
The Community Participation Plan took effect on 1 September 2026 and now applies to all councils and planning authorities in NSW. The Department received 629 formal submissions and 391 survey responses on the draft plan. Table 6, the list of development types excluded from exhibition, is on page 24.
Savings and transitional provisions are in place so that development applications and modification applications that were lodged but not yet determined before the commencement of the statewide Community Participation Plan on 1 September 2026.
You can read the final Community Participation Plan and the What we heard report on the NSW Planning Portal. The Department has also published answers to frequently asked questions on its Community Participation Plans page.
How Allen Price can help
Our town planning team can check whether your project falls within Table 6, advise on whether a clause 4.6 variation is worth pursuing, and prepare a Statement of Environmental Effects that addresses the amenity issues councils still assess. For subdivisions, our surveyors and civil engineers can help keep a project within the 5-lot threshold where that suits your goals. Get in touch with our Nowra, Kiama or Wollongong office to talk through what this means for your next development.